1 Excavation of GNSS Flood Flow canal from Km 46.000 to Km 57.700 and consruction of CM & CD works on EPC Basis in Kurnool District. Andhra Pradesh - Package 29
171.63
2 Modernisation of H.L.M.C Canals Package-1 & 6 under T.B.P.H.L.C System
153.10
3 JCR DLIS Phase-II 4L Distributory of RFMC of R.S.Ghanpur Reservoir
61.65
4 Construction of Saradhi Barrage with Vertical Lift Gates and other Appurtenant works across Mahanadi River in Chhattisgarh 
399.02
5 Sardar Sarovar (Narmada) Project - Construction of Garudeshwar Weir across River Narmada in Gujarat.
299.43 
6

Construction of Barrage and Desilting Chamber (Balancing works) Package for Tapovan Vishnugad Hydro Electric Power Project (4X130 MW) on the River Dhauliganga in Uttaranchal. (4X130 MW) on the River Dhauliganga in Uttaranchal.

437.56
7 Execution / Completion of Balance works of Bansagar Canal Project including canal lining and construction of new structures in District Sidhi (M.P.), Mirzapur and Allahabad (U.P.)
402.52
8 P.V. Narasimha Rao Thupakulagudem Project - Phase-I - Construction of Barrage across River Godavari at Thupakulagudem (v) on EPC Basis (Package-1)
805.44
9 Construction of New Anicut across Chitravathi River U/s existing Goddumarri Anicut near Goddumarri village, Ananthapuramu Dist, Andhra Pradesh
84.5548
10

HNSS Projects - Phase - II - Package No. 2 & 3 - Excavation and CM & CD works for HNSS Canal in Ananthapuramu Dist, Andhra Pradesh

192.263
11

HNSS Projects - Phase - II - Package No. 6 & 10 - Construction of Tunnels for HNSS Canal in Ananthapuramu Dist, Andhra Pradesh

70.993
12

HNSS Projects - Phase - II - Package No. 13, 17 & 9 - Excavation and CM & CD works for HNSS Canal in Ananthapuramu Dist, Andhra Pradesh

124.633
13

HNSS Project – Phase-II – Package 59 A - Excavation of Pungunur Branch Canal from km 150.000 to 173.000, CM & CD works, Tunnel, formation of summer storage tanks in Chittoor District, Andhra Pradesh

160.518
14 Excavation of GNSS Flood Flow canal from Km. 17.00 to Km. 34.00 (Balance work) including Construction of CM & CD works (7 Nos)- (Package 28 A) in Kurnool Dist., Andhra Pradesh
58.500
15 B.R.R. Vamsadhara Project - Construction of Side Weir Complex at Katragada (V); and Excavation of Flood Flow Canal from Km.0.000 to Km.13.447 including CC Lining, construction of CM & CD works; and Formation of Singidi Balancing Reservoir in Srikakulam District., Andhra Pradesh
162.920
16

HNSS Project Phase – II - Earth work Excavation of HNSS Kuppam Branch Canal , CM & CD works and 3 Lifts to feed an ayacut of 6300 Acres under tanks and to provide drinking water for 8 mandals in Palamaner and Kuppam constituencies on EPC Basis

430.26
17

RTPP – Stage – IV – Unit – 6 (1 x 600 MW) Balance of Plant Package

306.31
18 New Broad Gauge Railway Line from Obulavaripalle to Venkatachalam -Construction of Roadbed from KM 17/0 to 35/0 , construction of two Tunnels with ballastless track and earthwork in Formation, Major and Minor Bridges covering Kadapa and Nellore Districts of Andhra Pradesh  
470.29
19

GNSS Flood Flow Canal - Package - 27 - Construction of C.C Side Walls and Structures from Km 0.000 to upto Km 17.386

116.69
20 “Rehabilitation and Up-Gradation of Section II - Shirod Sahapur – Vasmat Section from KM 48/000 to KM 70/430 (NH - 752I) in the State of Maharashtra on EPC mode.
144.45
21 Rehabilitation and Up-Gradation of Section II - Jintur to Parbhani Section from Km 47/000 to Km 85/420 (NH - 752K) in the State of Maharashtra on EPC mode.
222.57
22 Rehabilitation and Upgradation of Section-I, Aurangabad-Sillod from km. 0+000 to km. 60+630 (NH-753F) in the State of Maharashtra on EPC mode.
304.22
23 Rehabilitation and Upgradation of Section-II, Sillod – Fardapur, From Km. 60+630 to Km. 99+660 (NH-753F) in the State of Maharashtra on EPC mode
225.33
24 Rehabilitation and Upgradation of Section-III, Fardapur-Jalgaon from km. 99+660 to km. 147+380 (NH-753F) in the State of Maharashtra on EPC mode.
308.61
25 Widening of HNSS Main Canal Phase-I from Km. (-) 1.150 to Km 78.670
343.35