The project involves the construction of the Greenfield Radial Road – Phase I, stretching from Chainage 0+000 to 19+200, covering a total length of 19.20 km with a 100-meter Right of Way. It is designed as a 3+3 six-lane divided carriageway, with provisions for future expansion to 4+4 lanes. A 20-meter-wide central median is reserved for a potential future Metro or rail corridor. The project includes three-lane service roads on both sides, along with dedicated cycle tracks, footpaths, greenbelts, and utility corridors. To ensure seamless connectivity, the scope also involves the construction of viaducts, underpasses, and major bridges, ultimately enhancing regional connectivity between the Outer Ring Road (ORR) and the Regional Ring Road (RRR).

Major Quantities

Earth Work
42 Lakh Cum

Granular Sub-base
2,51,919 Cum

Wet Mix Macadam (WMM)
2,47,125 Cum

Bituminous Works
1,47,476 Cum

Concrete Works
4,08,896 Cum

RE Wall
3,47,631 Sqm

address
Kadiri, Ananthpur Dist, Andhara Pradesh
Key Details

Value of Project
INR 1332.70 Crores

Client
Hyderabad Growth Corridor Limited

Location
Hyderabad

State
Telangana

Project Award Date
November 2025

Appointed Date
December 2025

Expected Completion By
May 2028

Project Length
19.2 Kms

Mode of Project
BOQ