Rithwik Projects Private Limited

Bengaluru Suburban Rail Project of Corridor – 4

Project Overview

Design and Construction of Civil, Architectural and E&M works of Nine (09 nos.) stations i.e., Elevated (Marathahalli – 1 nos.) and At-Grade (8 nos.) of Corridor-4 at Heelalige, Singena Agrahara, Huskur, Ambedkarnagar, Karmelaram, Bellandur, Doddanekundi & Kaggadasapura including Steel FOB, Roof Structures (PEB) and with all associated works of stations for Bengaluru Suburban Rail Project

Details of the Project

Scope
Construction of 9 Nos Metro Stations including MEP Works

Length of the Each Station
210m

Total No of Metro Stations
9 Nos (8 Nos -At Grade Stations and 1 No-Elevated Station)

Major Quantities

Concrete
94,798 Cum

Reinforcement Steel
8,469 MT

PEB Steel Works-Stations Area-Structural Steel
5805 MT

Roofing Work for Metro Stations
37,752 Sqm

Granite Works-Platform, concourse level and Other Areas
66,767 Sqm

address
Bangalore, Karnataka
Key Details

Value of Project
INR 554 Cr

Client
Rail Infrastructure Development Company (Karnataka) Limited (K RIDE)

Location
Bangalore-Corridor 4A B/W Heelaige-Kaggadaspura

State
Karnataka

Award Date
3/18/2025

Completion Date
3/18/2027