Kharghar – Turbhe Tunnel Road

Project Overview
Design, Construction and Commissioning of “Kharghar – Turbhe Tunnel Road (KTLR) For Direct Connectivity To International Corporate Park (ICP) at Kharghar, Navi Mumbai.
Major Quantities
Tunnel Excavation
7,89,541 Cum
Open Cut Excavation
5,42,286 Cum
Shotcrete
10,996 Cum
Tunnel lining with Gantry
56,962 Cum
Concrete
1,55,787 Cum
address
Kasheli, Thane Dist, Maharashtra
Key Details
Value of Project
INR 2099 Crores
Client
CIDCO
Location
Kharghar, Mumbai
State
Maharshtra
Award Date
October 19, 2023
Completion Date
September 20, 2028