EPC Contract Package covering Design & Engineering Services, Civil and Hydro- Mechanical Works of Sunni Dam HEP (382 MW)
Value of Project |
INR 1098.14 Crores |
Location |
Sunni |
State |
Himachal Pradesh |
Client |
SJVN Limited |
Award Date |
14.01.2023 |
Expected completion by |
November 2027 |
Height of the Dam |
83 Mtrs |
Length of the Dam |
178 Mtrs |
Type of Dam |
Concrete Gravity Dam |
Length & Dia of tunne |
3.60 Kms / 6.5 Mtr Dia and above |
Power House |
Underground (5×73 MW & 1×17 MW) |
Major Quantities |
Excavation |
9,00,000 Cum |
Concrete |
4,17,000 Cum |
Tunnel Excavation |
6,00,000 Cum |
Tunnel Concrete |
1,10,000 Cum |